A dynamic team was gathered to finish this task in two days. We are grateful for the assistance of the Carlyle Towers staff during these times of STRESS.
After many days of negotiations and discussions, a fire protection solution was found that created a loop system and removed the need to change existing main lines to distribute the water protection. This final phase allows installation of the long awaited wood flooring in the big new room of the condo. Once the Fire Marshall approves the installation, we can close all the holes which were needed to install our system. Test has been scheduled for the following morning.